NEM
MINIMUM SYSTEM LOAD
#146143
Actual Minimum System Load MSL1 condition in the SA Region on 07/11/2026
AEMO ELECTRICITY MARKET NOTICE Actual Minimum System Load MSL1 condition in the SA Region on 07/11/2026 AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the SA on 07/11/2026. The advisory MSL thresholds are: - MSL1: -160 MW - MSL2: -510 MW - MSL3: -710 MW The demand is below the MSL1 threshold. Demand refers to Operational Demand that excludes contribution from Significant Non-Scheduled Generation: see definitions at https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/operational-demand-data . Manager NEM Real Time Operations